Monthly Overview
This page provides ongoing construction updates for The Walk project throughout the month of March. Updates are posted weekly to keep the community informed about site activity and upcoming work.
Construction activities may vary depending on site conditions and weather.
Week 1
March 2-6
- Continued demolition and concrete crushing (recycling of existing pavement)
- Continued disassembly of monument signage (ongoing)
- Site grading activities (weather permitting)
Week 2
March 9-13
- Site grading activities (weather permitting)
Week 3
March 16-20
- Site grading activities (weather permitting)
- Fire hydrant installation to commence
- Storage of existing site monuments
Week 4
March 23-27
- Site grading activities (weather permitting)
- Fire hydrant installation to commence
March 30 - april 3
- Site grading activities (weather permitting)
- Fire hydrant installation to commence
- Garage foundation layout