Week 1
February 2-6
Week 2
February 9-13
Week 3
February 16-20
- Disassembly of existing monument signage
- Demolition and on-site concrete crushing for pavement recycling
- Removal of select trees within the project area
Week 4
February 23-27
- Continued demolition and concrete crushing (recycling of existing pavement)
- Continued disassembly of on-site monument signage
- Site grading activities (weather permitting)