Week 1
November 2 - 6
- Install elevator and stairs in the garage
- Continue retail building 1, 3, 4 and 5
- Continue elevator and stair cores at level 5
Week 2
November 9 - 13
- Install elevator and stairs in the garage
- Continue retail building 1, 3, 4 and 5
- Start elevator and stair cores at level 6
Week 3
November 16 - 20
Week 4
November 23 - 27