Monthly Overview
This page provides ongoing construction updates for The Walk project throughout the month of September. Updates are posted weekly to keep the community informed about site activity and upcoming work.
Construction activities may vary depending on site conditions and weather.
Week 1
August 31 - September 4
- Finish parking garage level 6 deck
- Continue the retail buildings
- Finish residential building north grade beam and start second level stair core
Week 2
September 7 - 11
Week 2
September 14 - 18
Week 3
September 21 - 25
Week 4
September 28 - October 2