Monthly Overview
This page provides ongoing construction updates for The Walk project throughout the month of August. Updates are posted weekly to keep the community informed about site activity and upcoming work.
Construction activities may vary depending on site conditions and weather.
Week 1
August 3 - 7
- Continue parking garage level 5 and level 6
- Continue the retail building
- Continue MR residential foundation
Week 2
August 10 - 14
- Continue parking garage level 6
- Continue the retail building
- Continue MR residential foundation
Week 3
August 17 - 21
- Finish parking garage level 6 concrete deck
- Continue the retail buildings
- Form and pour residential building stair core