Monthly Overview
This page provides ongoing construction updates for The Walk project throughout the month of July. Updates are posted weekly to keep the community informed about site activity and upcoming work.
Construction activities may vary depending on site conditions and weather.
Week 1
June 6 - 10
- Continue parking garage level 4
- Start the retail building CMU walls
- Start MR residential foundation