Monthly Overview
This page provides ongoing construction updates for The Walk project throughout the month of June. Updates are posted weekly to keep the community informed about site activity and upcoming work.
Construction activities may vary depending on site conditions and weather.
Week 1
June 1 - 5
- Continuing parking garage, starting third floor deck
- Residential underground plumbing
- Retail buildings underground plumbing
Week 2
June 8 - 12
- Continuing parking garage third floor deck
- Residential footing excavation
- Retail buildings underground utility and footing
Week 3
June 15 - 19
- Continuing parking garage third floor deck
- Install retail building foundation
- Continue residential underground trenching
Week 4
June 22 - 26
- Proceed to Level 4 of the parking garage.
- Continue residential underground trenching
- Install retail building foundation
Week
June 29 - July 3
- Continue parking garage level 4
- Continue residential underground trenching
- Start MR residential foundation