Monthly Overview
This page provides ongoing construction updates for The Walk project throughout the month of May. Updates are posted weekly to keep the community informed about site activity and upcoming work.
Construction activities may vary depending on site conditions and weather.
Week 1
May 4 - 8
- Parking garage second floor
- Excavation and grading (residential and retail)
- Water meter installation on Norwalk Blvd
Week 2
May 11 - 15
- Continuing parking garage second floor deck
- Excavation and grading (residential and retail)
- Waterline installation on Avenida Manuel Salinas